Screening request for an 80MW Solar & Battery Farm submitted to The Consents Unit
November 2020
The Consents Unit response to Screening request - No EIA required
February 2021
Pre Application Consultation with Community
September 2021
2nd Pre Application Consultation with Community
October 2021
Submission of planning application for 80MW Battery Energy Storage System Only - Phase 1
February 2022
Public Notices of submitted Phase 1 Application
February 2022
Deadline for Public Comment on application for Phase 1
May 2022
Re-screening request to The Consents Unit for Phase 2 Solar Farm
April 2022